Adygea Wind Farm
The Adygea Wind Farm is located on the border of the Giaginsky and Shovgenovsky Districts, Republic of Adygea. Being Rosatom’s first completed wind energy project, it has been supplying electricity to the wholesale electricity market since 1 March 2020.
The wind farm consists of 60 wind turbines with a capacity of 2.5 MW each. With an installed capacity of 150 MW, it is planned to generate 354 million kWh of electricity per annum, or 20% of total electric energy consumed in the region. During its operation period, the wind farm will occupy an area of 60 hectares. Investments in the project amounted to RUB 23 billion.
As confirmed by the Russian Ministry of Industry and Trade, 55% of the wind farm equipment is sourced locally.
Wind turbines at the Adygea Wind Farm are 150 meters high (measured at the rotor's top). Each 50-meter blade weighs 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure weighs about 320 tonnes.
Kochubeevskaya Wind Farm
The Kochubeevskaya Wind Farm is located in the Kochubeevsky District, Stavropol Krai. It has been supplying electricity to the wholesale electricity market since January 2021.
The wind farm consists of 84 wind turbines with a capacity of 2.5 MW each. With an installed capacity of 210 MW, it is planned to generate 597 kWh of electricity on the annual average. During its operation period, the wind farm will occupy an area of 75 hectares. Investments in the project exceeded RUB 28 billion.
As confirmed by the Russian Ministry of Industry and Trade, 65% of the wind farm equipment is sourced locally.
Wind turbines at the Kochubeevskaya Wind Farm are 150 meters high (measured at the rotor's top). Each 50-meter blade weighs 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure weighs about 320 tonnes.
Karmalinovskaya Wind Farm
The Karmalinovskaya Wind Farm is located near Novoaleksandrovsk, Stavropol Krai. It has been supplying electricity to the wholesale electricity market since 1 April 2021.
The wind farm consists of 24 wind turbines with a capacity of 2.5 MW each. With an installed capacity of 60 MW, it is planned to generate 147 million kWh of electricity on the annual average. Investments in the project amounted to RUB 8 billion.
As confirmed by the Russian Ministry of Industry and Trade, 68% of the wind farm equipment is sourced locally.
The Karmalinovskaya Wind Farm uses parts and components fully produced and assembled in Russia.
Wind turbines at the Karmalinovskaya Wind Farm are 150 meters high (measured at the rotor's top). Each 50-meter blade weighs 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure weighs about 320 tonnes.
Marchenkovskaya Wind Farm
The Marchenkovskaya Wind Farm is located in the Zimovnikovsky District, Rostov Region. It has been feeding electricity into the national power grid since July 1, 2021.
The farm consists of 48 wind turbines with a capacity of 2.5 MW each. With an installed capacity of 120 MW, it is planned to generate more than 402 million kWh of electricity on the annual average. Investments in the project amounted to about RUB 16 billion.
As confirmed by the Russian Ministry of Industry and Trade, 68% of the wind farm equipment is sourced locally.
The Marchenkovskaya Wind Farm uses parts and components fully produced and assembled in Russia.
Wind turbines at the Marchenkovskaya Wind Farm are 150 meters high (measured at the rotor's top). Each 50-meter blade weighs 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure weighs about 320 tonnes.
Bondarevskaya Wind Farm
The Bongarevskaya Wind Farm is located in the Ipatovsky District, Stavropol Krai. It has been feeding electricity into the national power grid since September 1, 2021. This is third wind farm in the Stavropol Krai.
The farm consists of 48 wind turbines with a capacity of 2.5 MW each. With an installed capacity of 120 MW, it is planned to generate more than 354 million kWh of electricity on the annual average.
As confirmed by the Russian Ministry of Industry and Trade, 68% of the wind farm equipment is sourced locally.
The Bongarevskaya Wind Farm uses parts and components fully produced and assembled in Russia.
Wind turbines at the Bondarevskaya Wind Farm are 150 meters high (measured at the rotor's top). Each 50-meter blade weighs 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure weighs about 320 tonnes.
Medvezhenskaya Wind Farm
The Medvezhenskaya wind farm is located on the territory of the Trunovsky Municipal District of the Stavropol Territory. Since December 1, 2021, the WPP has started to supply electricity and capacity to the unified grid of the country.
As part of the wind farm, 24 wind turbines with a capacity of 2.5 MW each operate. The installed capacity of the wind farm is 60 MW. The planned average annual energy production is 171 million kWh.
The degree of localization of the facility's equipment, confirmed by the Ministry of Industry and Trade of the Russian Federation, was 68%.
The height of the wind turbine at the Medvezhenskaya wind farm (together with the rotor) will be 150 m. The length of the blades is 50 m, and the weight of each is 8.6 tons. The tower itself weighs about 200 tons, the generator – 52 tons. The total weight of the structure is approximately 320 tons.
Berestovskaya Wind Farm
Berestovskaya wind farm is located on the territory of Petrovsky district of Stavropol Krai. Since January 1, 2023, the WPP has started to supply electricity and power to the unified grid of the country.
As part of the wind farm, 24 wind turbines with a capacity of 2.5 MW each operate. The installed capacity of the wind farm is 60 MW. The planned average annual energy production is 175.5 million kWh.
The height of the wind turbine at the Berestovskaya wind farm (together with the rotor) is 150 m. The length of the blades is 50 m, and the weight of each is 8.6 tons. The tower itself weighs about 200 tons, the generator – 52 tons. The total weight of the structure is approximately 320 tons.
Kuzminskaya Wind Farm
The permit for the construction of the Kuzminskaya WPP was received in May 2022.
The wind farm will be located on the territory of the Kochubeyevsky municipal district of the Stavropol Territory.
The installed capacity of the wind farm will be 160 MW. 64 wind turbines with a capacity of 2.5 MW each will be installed at the site. The planned average annual energy production is 378 million kWh.
The height of the wind turbine at the Kuzminskaya wind farm (together with the rotor) will be 150 m. The length of the blades is 50 m, and the weight of each is 8.6 tons. The tower itself weighs about 200 tons, the generator – 52 tons. The total weight of the structure is approximately 320 tons.
Trunovskaya Wind Farm
The construction permit for the Trunovskaya Wind Farm was obtained in June 2022.
The farm will be located in the Trunovsky District, Stavropol Krai.
A total of 38 wind turbines with a capacity of 2.5 MW each will be erected on the site. The Trunovskaya Wind Farm will be constructed and commissioned in two phases:
• 24 wind turbines with an aggregate capacity of 60 MW will be installed and put into operation during the first phase;
• 14 wind turbines with a total capacity of 35 MW will be constructed during Phase II of the project.
With an installed capacity of 95 MW, the wind farm is estimated to generate 225 million kWh per annum.
Wind turbines at the Trunovskaya Wind Farm will be 150 meters high (measured at the rotor's top). Each 50-meter blade will weigh 8.6 tonnes. Together with a 200-tonne tower and a 52-tonne generator, the entire structure will weigh about 320 tonnes.